Reinforcement · Published 28 September 2026 · Updated 10 November 2026

Steel weight per metre: rebar chart and D²/162 formula

Weight calculation follows a specified bar diameter and length. It does not determine reinforcement size, spacing, laps or the steel required by a structural design.

On this pageQuick answerWhere D²/162 comes fromWorked quantity example: a 12 mm grid12 m stock and a cutting scheduleWhy kg of steel per m³ is not a design rule

Quick answer

For a nominal round steel bar, kg/m ≈ D²/162 when D is in millimetres. A 12 mm bar is about 0.889 kg/m, or 10.667 kg for 12 m. Manufacturer nominal-mass tables may differ slightly through rounding and production tolerances.

· Updated · Qatar Steel: reinforcing steel product specifications

Metric rebar weight chart for 8–32 mm bars, showing approximate kilograms per metre and per 12 m bar using D²/162.
Metric rebar weight chart for 8–32 mm bars, showing approximate kilograms per metre and per 12 m bar using D²/162. Illustrative geometry; use the written dimensions in the worked example.

Where D²/162 comes from

A round bar's cross-section is πD²/4. Convert the diameter from millimetres to metres, multiply the area by one metre of length and then by an assumed steel density of 7,850 kg/m³. That gives 0.0061654D² kg/m, close to D²/162.

The shortcut is theoretical mass for the nominal diameter. Manufacturer tables use nominal values and applicable tolerances. Use the supplier's documentation for the purchase and weighbridge reconciliation. A ribbed bar is identified by its nominal diameter; measuring across rib tips and treating that as a smooth solid cylinder is incorrect.

Approximate theoretical mass using D²/162; 12 m length before cuts
Diameterkg per metrekg per 12 m bar
8 mm0.3954.741
10 mm0.6177.407
12 mm0.88910.667
16 mm1.58018.963
20 mm2.46929.630
25 mm3.85846.296
32 mm6.32175.852

Worked quantity example: a 12 mm grid

Consider an illustrative single-layer grid with bar centrelines at the boundaries of a 4 × 3 m centreline rectangle and maximum spacing 200 mm in both directions. Bars running 4 m long are spaced across 3 m: 3 ÷ 0.2 + 1 = 16. Bars running 3 m long are spaced across 4 m: 4 ÷ 0.2 + 1 = 21.

Total straight centreline length is 16 × 4 + 21 × 3 = 127 m. With the D²/162 shortcut, mass is 127 × 12² ÷ 162 = 112.89 kg. An illustrative 10% purchasing allowance makes it 139.7 m and 124.18 kg, but it does not calculate actual lap lengths or a cutting schedule.

The 4 × 3 m rectangle is explicitly a bar-centreline example, not the concrete edge. Actual cover, bends, anchorage, overlaps, starter bars, extra supports and multiple layers must be taken from the reinforcement drawings. The existing slab-grid tool uses US bar numbers; use the metric steel-weight tool for a true 12 mm weight.

12 m stock and a cutting schedule

Dividing total length by 12 m gives only a theoretical lower bound on stock bars. In the example, a single 12 m bar can provide three 4 m cuts or four 3 m cuts before considering cutting allowances, but mixing those cuts may leave unusable offcuts. Work through each required cut length and reuse policy.

Separate drawing laps from handling loss. A flat percentage cannot establish the lap length required at a given location. Price straight bars, cut-and-bent service, transport and waste separately where the supplier quotes them separately.

Why kg of steel per m³ is not a design rule

A slab, beam, column and footing carrying different loads can have very different reinforcement intensity. Structural system, spans, loading and detailing change the bar schedule. This guide intentionally supplies no universal kg/m³ reinforcement recommendation.

After a design schedule exists, you can divide its total reinforcement mass by the corresponding concrete volume as a project comparison ratio. Label the elements and revision. That historical ratio is useful for checking an estimate, but applying it to a new building does not replace its design. Published early-estimate ranges, and where those sources disagree, are in rebar kilograms per cubic metre of concrete. Sheet weights for square meshes A142, A193, A252 and A393, and a sheet count after a stated lap, are in BRC mesh sheets and weight per slab. Dated dirham and riyal prices per ton, where a page was opened, are in rebar price per ton in the UAE and rebar price per ton in Saudi Arabia.

Questions people ask

How much does a 12 mm, 12 m bar weigh?

The D²/162 shortcut gives 10.667 kg. Check the manufacturer's nominal mass and tolerances for the bar being purchased.

Is a US #4 bar the same as a 12 mm bar?

No. US bar designations are a different size system. Use the specified designation or metric diameter, not a visual substitute.

Can I order from total kg alone?

Include diameter, grade, lengths or bending schedule, quantity and required certification. An equal mass of the wrong size is not an equivalent reinforcement order.

Sources and calculation basis

Source links support the points named beside them. Worked quantities are Construclytic calculations using the assumptions shown above. A price in a table is the figure that source printed on the date it was read. It is not a quotation for your site, and it does not replace the project specification.

  1. Qatar Steel: reinforcing steel product specificationsManufacturer reference for bar sizes and nominal mass. The worked grid below is an independent quantity example.