Metric takeoffs for Qatar and the GCC

Construclytic is built in Doha. The same published formulas run in imperial or metric. For a villa pad in Qatar, switch units on the calculator instead of converting a cubic-yard ticket in your head.

On this pageAnswerSwitch the tool, do not back-calculate yardsWhat stays the same

Worked example — 6.0 m × 3.6 m × 100 mm slab, 8% waste

Net volume is 6.0 × 3.6 × 0.10 = 2.16 m³. With 8% waste that is 2.33 m³, which rounds to a 2.4 m³ order on a 0.1 m³ step. The same pad in imperial is the homepage 20 × 12 × 4 in example — pick one unit system and stay there.

Updated

Length unit converter: measurement diagram. Use the calculator's field labels and units. Apply its stated allowance and rounding to the calculated result.
Use the calculator's field labels and units. Apply its stated allowance and rounding to the calculated result. View image

Free template

Free villa BOQ workbook

The villa BOQ workbook is free. It is a blank Excel file for a house bill of quantities: a Start sheet, 22 lines in two sections (substructure and superstructure), and a Summary sheet. You enter the quantity and the rate. The amount is quantity × rate. The download has no email gate, and it does not fill in a Qatar, UAE or Saudi price. Construclytic Pro is planned and is not available. The waitlist page says the expected price is about $12 per month and that the figure may change. Joining the list does not start a subscription.

Switch the tool, do not back-calculate yards

A 100 mm interior slab is the usual cousin of a 4 in US pad. Ready-mix in Doha and the wider GCC is sold in cubic metres, commonly rounded to 0.1 m³. Construclytic’s metric mode uses those units on the inputs so the formula ID still explains the letter.

Display currency can show QAR, AED or SAR. That converts the planning rate you typed. It is not a live plant or quarry feed and not a municipality price list.

What stays the same

Waste, purchase rounding and the planning boundary do not change because the job is in Qatar. Hot weather, pump lines and tight villa access still eat waste. Record the percentage.

Block walls, compound walls and metal fences are common on the peninsula. The wood-fence tool is still a run count — do not treat it as a boundary-wall spec.

Do it in order

  1. Open the calculator and choose metric before you type dimensions.
  2. Enter millimetres for thickness and metres for plan size.
  3. Keep waste visible, then replace the planning rate with a dated plant or quarry quote.

Planning boundary

This is a unit-system method. It is not a Qatar building-code approval, a municipality stamp or a live GCC price index.

Sources

This guide is original worked arithmetic for the calculator linked above. It does not cite a laboratory test or a supplier price. The method, the internal check and the planning limit are on How we calculate.

Should I type metres and then convert to yards?

No. Switch the calculator to metric. Mixed units on one line are how orders go short.

Does QAR mean the plant quoted you?

No. Currency is a display conversion of the planning rate you entered.

Is this a Qatar building-code check?

No. Local approvals, soil and mix design still sit with the responsible professional.