Concrete calculator

Sonotube calculator

four 12 in tubes filled 48 in with 10% waste round to a 0.75 yd³ ready-mix order. The same default inputs in metric give 0.4 m³.

Formula. π × (diameter ÷ 2)² × height × count ÷ 27 × (1 + waste) → ready-mix order

Solid cardboard-tube volume, ready-mix order and bags. Post-hole annulus is a different tool when a post occupies the hole.

By Feroz Sheikh · Our math isn't hidden: see the formula, waste allowance and rounding rule. Formula CONC-SONO-001 v1.1.0

Math shown

See the formula, waste and rounding.

Formula IDCONC-SONO-001v1.1.0

Project inputs

Enter your measurements. Switching units converts the same project, including coverage and unit rates. Package yields keep the unit printed beside each field.

Refine measurements and rates at any time. Your current values are included in the material-list PDF.

Calculated result

0.75yd³

Ready-mix order

Formula, waste and rounding are shownCONC-SONO-001

π × (diameter ÷ 2)² × height × count ÷ 27 × (1 + waste) → ready-mix order

12.57 ft³

Net volume

Planning estimate, not engineering advice. Confirm site measurements and product specifications. Calculation limits.

Bag table · waste in

Counts round up. A cubic yard is 45 of 80 lb, 60 of 60 lb, 72 of 50 lb, 90 of 40 lb.

BagCount
40 lb47
50 lb37
60 lb31
80 lb24
Sonotube: measurement diagram. Use the inside form diameter and full concrete height. Diameter is twice the radius.
Use the inside form diameter and full concrete height. Diameter is twice the radius. View image

Each tube is a solid cylinder: π × (diameter ÷ 2)² × height × count. Ready-mix rounds to the next 0.25 yd³ after waste. The post is not subtracted.

  1. Measure inside diameter of the form and the fill height, not the cardboard wall.
  2. If a wood post occupies the hole, use the post-hole calculator instead.
  3. Bag equivalents sit beside the truck quantity.

Add your project costs

Enter supplier prices and any labour, equipment or delivery costs. Pick a currency — badges, inputs, and totals follow.

Enter your supplier’s ready-mix concrete rate in the selected unit. Add delivery, pumping, short-load fees and placing labour as separate project costs. For GCC projects, select QAR, AED, SAR, KWD, OMR or BHD and enter local supplier rates.

View estimate Quote / invoice Add another item

How this calculator works

A transparent sonotube takeoff.

Each tube is a solid cylinder: π × (diameter ÷ 2)² × height × count. Ready-mix rounds to the next 0.25 yd³ after waste. The post is not subtracted.

CONC-SONO-001 is a solid cardboard-tube cylinder. The post is not subtracted. Post-hole is the annulus tool when a wood post occupies the hole. Mixing the two formulas shorts the truck. Ready-mix still rounds to the next 0.25 yd³ after waste.

Worked example. Example: four 12 in tubes filled 48 in with 10% waste round to a 0.75 yd³ ready-mix order.
See the example inputs and calculated result

This separate example uses the calculator's starting values in imperial units. It stays unchanged when you edit the tool above. Example rates, yields and dimensions are assumptions, not recommendations for your project.

Sonotube: example inputs
InputExample value
Tube diameter12 in
Fill height48 in
Number of tubes4 count
Waste factor10 %

Example result: Ready-mix order — 0.75 yd³.

π × (diameter ÷ 2)² × height × count ÷ 27 × (1 + waste) → ready-mix order

Use the labelled units above when reproducing this example. To work in metric, switch the calculator to Metric; applicable measurements are converted, while product-specific units remain labelled.

  1. 1. Measure inside diameter of the form and the fill height, not the cardboard wall.
  2. 2. If a wood post occupies the hole, use the post-hole calculator instead.
  3. 3. Bag equivalents sit beside the truck quantity.

Field notes that change the number

  • Measure inside diameter of the form and the fill height, not the cardboard wall.
  • If a wood post occupies the hole, use the post-hole calculator instead.
  • Diameter, depth and steel come from the approved design.

Common mistakes

  • Using post-hole and subtracting a post that is not there.
  • Treating this as a pier size or soil-bearing design.
  • Ordering the net volume and skipping plant increments.

Need the broader workflow? Read the concrete planning guide.

How-to: Tapered round footing volume: use a frustum, not an average diameter · Concrete for solid tube forms: diameter, height and tube count · How to fill fence and deck post holes

Questions

Questions about sonotube

Why not post-hole?

Post-hole subtracts the post. A sonotube pier is usually poured solid. Mixing the two formulas short the truck.

Does this size the pier?

No. Diameter, depth and steel come from the approved design.

What is the formula ID?

This sonotube calculator publishes formula CONC-SONO-001, version 1.1.0. The ID stays on the result and on the estimate line.