Calculated result
Cement bags to batch
CONC-MIX-001dry volume = wet volume × dry factor; each material = dry volume × parts ÷ total parts
Cement volume
Sand volume
Aggregate volume
Concrete calculator
Volumetric cement, sand and aggregate split from a known wet volume using a stated mix ratio and dry-volume factor.
By Feroz Sheikh · Formula CONC-MIX-001 v1.0.1 · Tested formula
CONC-MIX-001v1.0.1Enter your measurements. Switching units converts the same project, including coverage and unit rates. Package yields keep the unit printed beside each field.

Calculated result
Cement bags to batch
CONC-MIX-001dry volume = wet volume × dry factor; each material = dry volume × parts ÷ total parts
Cement volume
Sand volume
Aggregate volume
Planning estimate, not engineering advice. Confirm site measurements and product specifications. Calculation limits.
This calculator splits a known wet concrete volume into cement bags, sand and coarse aggregate using a stated volumetric ratio and a documented dry-volume factor — not a strength mix design.
Enter supplier prices and any labour, equipment or delivery costs. Pick a currency — badges, inputs, and totals follow.
Enter your supplier’s ready-mix concrete rate in the selected unit. Add delivery, pumping, short-load fees and placing labour as separate project costs. For GCC projects, select QAR, AED, SAR, KWD, OMR or BHD and enter local supplier rates.
How this calculator works
This calculator splits a known wet concrete volume into cement bags, sand and coarse aggregate using a stated volumetric ratio and a documented dry-volume factor — not a strength mix design.
CONC-MIX-001 splits a known wet volume into cement, sand and aggregate using a stated mix ratio. It is a volumetric batch, not a mix design and not a strength stamp. Formula ID stays so the ratio is not a hidden 1:2:3.
This separate example uses the calculator's starting values in imperial units. It stays unchanged when you edit the tool above. Example rates, yields and dimensions are assumptions, not recommendations for your project.
| Input | Example value |
|---|---|
| Wet concrete volume | 1 yd³ |
| Cement parts | 1 ratio |
| Sand parts | 2 ratio |
| Aggregate parts | 4 ratio |
| Dry-volume factor | 1.54 ratio |
| Cement bag yield | 1 ft³ / bag |
| Waste factor | 0 % |
Example result: Cement bags to batch — 6 bags.
dry volume = wet volume × dry factor; each material = dry volume × parts ÷ total parts
Use the labelled units above when reproducing this example. To work in metric, switch the calculator to Metric; applicable measurements are converted, while product-specific units remain labelled.
Need the broader workflow? Read the concrete planning guide.
Questions
No. Volumetric parts do not replace an ACI or supplier mix design, water-cement ratio or trial batch.
Many field manuals multiply wet volume by about 1.54 to estimate dry material volume. Replace it when you have a measured yield.
This concrete mix calculator publishes formula CONC-MIX-001, version 1.0.1. The ID stays on the result and on the estimate line.